Previous years Time and Work Quant Questions for SSC CGL Exams-2017

Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_0.1
Dear Students, SSC has released the notification for CGL 2017. This time again the competition is going to be very stiff. Questions from Quant are asked in Tier-1 and Tier-II as well. Hence, you need to focus on this subject more. The only trick to master Quant is “practice‘. So, Practice daily. We are providing topic-wise quant quizzes, solve, learn, succeed.

Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_1.1
Q2. There is sufficient food for 400 men for 31 days. After 28 days 280 men leave the place. For how many days will the rest of the food last for the rest of the men?
(a) 5 days
(b) 10 days
(c) 12 days
(d) 15 days
Q3. A work could be completed in 100 days by some workers. However, due to the absence of 20 workers, it was completed in 110 days. The original number of workers was
(a) 100
(b) 220
(c) 55
(d) 50
Q4. A can write 75 pages in 25 hrs. A and B together can write 135 pages in 27 hrs. In what time can B write 48 pages?
(a) 17 hrs.
(b) 19 hrs.
(c) 24 hrs.
(d) 23 hrs.
Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_2.1
Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_3.1
Q6. A is twice as good a workman as B, and together they finish a work in 12 days. In how many days can it be done by each separately?
(a) 18 days, 36 days
(b) 22 days, 24 days
(c) 23 days, 25 days
(d) Can’t be determined
Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_4.1
Q8. A certain number of men complete a work in 160 days. If there were 28 men more, the work could be finished in 20 days less. How many men were originally there?
(a) 116
(b) 122
(c) 124
(d) 196
Q9. A and B, working separately, can mow a field in 12 and 15 hours respectively. They work alternately, each for one hour, with A beginning at 5 a.m. At what time will the mowing be completed?
(a) 5: 30 pm
(b) 4: 30 pm
(c) 6: 15 pm
(d) 6: 30 am

Q10. A and B together can complete a work in 8 days and B and C together in 12 days. All of them together can complete the work in 6 days. In how much time will B and C together complete the work?
(a) 8 days
(b) 10 days
(c) 12 days
(d) 20 days


Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_3.1


Q11. 5 men can prepare 10 toys in 6 days working 6 hours a day. Then in how many days can 12 men prepare 16 toys working 8 hrs a day?
(a) 5 days
(b) 3 days
(c) 4 days
(d) 6 days

Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_6.1
Previous years Time and Work Quant Questions for SSC CGL Exams-2017 – Latest SSC jobs_7.1
Q14. A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time then B left the work. If A completed the rest of the work in 10 days, then B worked for
(a) 6 days
(b) 8 days
(c) 12 days
(d) 16 days

CRACK SSC CGL 2017



More than 2400+ Candidates were selected in SSC CGL 2016 from Career Power Classroom Programs.


9 out of every 10 candidates selected in SSC CGL last year opted for Adda247 Online Test Series.

[banner_management slug=previous-years-time-and-work-quant-ssc-2017]
QR Code
Scan Me