RRB NTPC Mathematics Quiz : 26th August

Dear aspirants,

As you all know, RRB NTPC Exam will be held in the month of September-October 2019. So we are here to help you with the Mathematics subject. We are providing daily quantitative aptitude quizzes, which will help you to score good marks in this section. We aim to provide the best study material to our readers with exam level questions to help them get used to the recent pattern. Attempt this quiz and check your preparation.

Q1. There are five bells which start ringing together at intervals of 3, 6, 9, 12 and 15  seconds respectively. In 36 minutes, how many times will the bells ring simultaneously? 
पांच घंटियाँ हैं, जो क्रमशः 3, 6, 9, 12 और 15 सेकण्ड के अंतराल पर बजना प्रारंभ करती हैं। 36 मिनट में, वह घंटियाँ कितनी बार एक-साथ बजेंगीं? 
(a) 13
(b) 12
(c) 6
(d) 5

S1. Ans. (a);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_0.1

Q2. n is a whole number which when divided by 4 gives the remainder 3. The remainder when 2n is divided by 4 is 
 n एक पूर्ण संख्या है, जिसे जब 4 से विभाजित किया जाता है, तो शेषफल 3 प्राप्त होता है। जब 2n को 4  से विभाजित किया जाए, तो शेषफल है?
(a) 1
(b) 2
(c) 3
(d) 0

S2. Ans. (b);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_1.1

Q3. A wall clock gains 2 minutes in 12 hours, while a table clock loses 2 minutes every 36 hours. Both are set right at 12 noon on Tuesday. The correct time when both show the same time next would be
एक दीवार घड़ी प्रत्येक 12 घंटे में 2 मिनट आगे हो जाती है, जबकि एक मेज घड़ी प्रत्येक 36 घंटे में 2 मिनट पीछे हो जाती है। दोनों को मंगलवार को दोपहर 12 बजे सही सेट किया गया। वह सही समय, जब दोनों घड़ियाँ अगली बार समान समय दर्शायेंगी 
(a) 12.30 at night, after 130 days
(b) 12 noon, after 135 days
(c) 1.30 at night, after 130 days
(d) 12 midnight, after 135 days

S3. Ans. (b);
Sol.
The wall clocks gains 6 min in 36 hours, while table watch loses 2 min. in 36 hour.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_2.1

Q4. A and B started a business by investing Rs. 3,50,000 and Rs. 1,40,000 respectively. A gets 20% of the yearly profit for managing the business. Thereafter the profit is divided in the ratio of the capital. If A receives totally Rs. 38,000 more than B at the end of a year, then the total  profit is 
A और B ने क्रमशः 3,50,000 रु. और 1,40,000 रु. का निवेश करके एक व्यवसाय शुरू किया। A व्यवसाय के प्रबंधन के लिए वार्षिक लाभ का 20% प्राप्त करता है। उसके बाद लाभ को पूँजी के अनुपात में बांटा गया। यदि A, वर्ष के अंत में B से कुल 38,000 रु. अधिक प्राप्त करता है, तो कुल लाभ है- 
(a) Rs. 28,000
(b) Rs. 2,80,000
(c) Rs. 1,05,000
(d) Rs. 70,000

S4. Ans. (d);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_3.1

Q5. A does one-fifth of a work in a week. B finishes the same in a fortnight. B starts the work and works only for 3 days. Thereafter A completes the job. He will finish it in 
A एक सप्ताह में एक कार्य का 1/5 करता है। B समान कार्य को एक पखवाड़े में पूरा करता है। B कार्य करना प्रारंभ करता है और केवल 3 दिन कार्य करता है। उसके बाद A कार्य पूरा करता है। वह इसे कितने दिनों में पूरा करेगा?  
(a) 10 days
(b) 7 days
(c) 12 days
(d) 28 days

S5. Ans. (d);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_4.1

Q6. A tank can be filled by pipe A in 2 hours and pipe B in 6 hours. At 10 A.M. pipe A was opened. At what time will the tank be filled if pipe B is opened at 11 A.M. ? 
एक टंकी को पाइप A द्वारा 2 घंटे में भरा जा सकता है और पाइप B द्वारा 6 घंटे में। 10 पूर्वाह्न पाइप A को खोल दिया गया। यदि पाइप B को 11 पूर्वाह्न खोला गया, तो वह टंकी किस समय पर भर जायेगी?
(a) 12.45 A.M.
(b) 5 P.M
(c) 11.45 A.M.
(d) 12  P.M.

S6. Ans. (c);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_5.1

Q7. A swimming pool has 3 drain pipes. The first two pipes A and B, operating simultaneously, can empty the pool in half the time that C, the 3rd pipe, alone takes to empty it. Pipe A, working alone, takes half the time taken by pipe B. Together they take 6 hours 40 minutes to empty the pool. Time taken by pipe A to empty the pool, in hours, is  
एक स्विमिंग पूल में 3 निकासी पाइप हैं। पहले दो पाइपों A और B को, एकसाथ संचालित करके, पूल को उससे आधे समय में खाली किया जा सकता है, जितना समय तीसरा पाइप, C, अकेले इसे खाली करने में लेता है। पाइप A, अकेले कार्य करके, पाइप B द्वारा लिए गए समय से आधा समय लेता है। वे मिलकर पूल को खाली करने में 6 घंटे 40 मिनट लेते हैं। पूल को खाली करने में पाइप A द्वारा लिया गया समय, घंटे में, है-  
(a) 15
(b) 10
(c) 30
(d) 7

S7. Ans. (a);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_6.1

Q8. A can do a certain work in 12 days. B is 60% more efficient than A. How many days will B and A together take to do the same job? 
A एक निश्चित कार्य को 12 दिनों में कर सकता है। B, A से 60% अधिक कार्यकुशल है। B और A मिलकर समान कार्य को करने में कितने दिन लेंगे? 
(a)  80/13
(b)  70/13
(c)  75/13
(d)  60/13

S8. Ans. (d);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_7.1

Q9. 2 men and 4 boys can do a piece of work in 10 days, while 4 men and 5 boys can do it in 6 days. Men and boys are paid wages according to their output. If the daily wage of a man is Rs. 40, then the ratio of daily wages of a man and a boy will be 
2 पुरुष और 4 लड़के एक कार्य को 10 दिनों में कर सकते हैं, जबकि 4 पुरुष और 5 लड़के इसे 6 दिनों में कर सकते हैं। पुरुष और लड़कों को उनके आउटपुट के अनुसार मजदूरी का भुगतान किया गया। यदि एक पुरुष की दैनिक मजदूरी 40 रु. है, तो एक पुरुष और एक लड़के की दैनिक मजदूरी का अनुपात होगा
(a) 5 : 3
(b) 5 : 2
(c) 7 : 4
(d) 7 : 3

S9. Ans. (b);
Sol.
RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_8.1

 

Q10. A, B and C can do a piece of work in 30, 20 and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish? 
A, B और C एक कार्य को क्रमशः 30, 20 और 10 दिनों में कर सकते हैं। A की मदद बारी-बारी से एक दिन B करता है और अगले दिन C करता है, कार्य पूरा होने में कितना समय लगेगा? 
(a) 9(3/8)  days
(b) 4(3/8)  days
(c) 8(3/8)  days
(d) 10(3/8)  days

S10. Ans. (a);
Sol.

RRB NTPC Mathematics Quiz : 26th August – Latest SSC jobs_9.1